Corona-maatregelen bouwplaats
23-06-2020

Three questions to Peter van Hoogstraten of OpenIJ

In recent months, the corona crisis has also reached the new sea lock in IJmuiden. OpenIJ started taking measures at the construction site at a very early stage. Peter van Hoogstraten is project leader at OpenIJ for the eastern part of the lock in IJmuiden. We asked him three questions about this.
Nieuwe zeesluis in beeld met nummeraanduiding van de werkzaamheden in mei en juni 2020
11-05-2020

New sea lock, what's happening in May and June 2020?

The following works will be carried out in May and June: The western part of the Middle Lock island will be cleared, the cofferdam for the lock sill of the outer head will be removed, and testing will be carried out on the new lock gates in Amsterdam and IJmuiden.
vlag wappert op hoogste punt Sluis Operatie Centrum in aanbouw
29-10-2018

Lock Operation Centre of the new sea lock at IJmuiden reaches its highest point

One year after the start of the construction of the Lock Operation Center on 9 October 2017, the contours of the striking object halfway along the southern lock chamber wall are clearly visible. A distinctive characteristic of the design is that the 18 metre high building inclines towards the lock at an angle of 15 degrees.