Works at Vissershaven IJmuiden
2025/45
From
30 Jun 2025
until
12 Oct 2025
Area - Lock
The Port of IJmuiden is investigating the possibilities for adjusting the maintenance depth of the Halkade Vissershaven at Halls C, D and E. The following activities will be carried out for this purpose:
- Maintenance dredging work (period: 30-06-25 to 12-10-25);
- Research into explosive remnants of war (period: 28-07-25 to 17-08-25);
- Ridge wall test t.h.v. Halkade (period: 25- 08- 25 t/m 31- 08- 25)
PreSail IJmuiden
During the PreSail IJmuiden on 18 and 19 August and when departure for the locks in the morning of 20 August, no work will be carried out on the water.