The new sea lock - what's happening in July and August

News item
02-07-2019
nieuwe zeesluis zomer 2019

OpenIJ is continuing construction activities at the new sea lock during the summer months. These activities include the sinking operation of the inner lock head (number 1 in the picture), construction work to connect the dividing wall to the outer lock head (number 2 in the picture), and work on the northern and southern lock chamber walls as well as on the future lock chamber itself (number 3 in the picture). Work on the local control buildings, the lock sill cofferdam, and completion works to the lock gates will also continue (number 4 in the picture).

The sinking operation of the lock gate chamber for the inner head

The sinking operation of the lock gate chamber for the inner head has started. With a length of 80 metres, a width of 55 metres and a height of 25 metres, this lock gate chamber is twice as big as that of the outer head. It provides space for both the inner lock gate (on the North Sea Canal side) and the spare lock gate. Centimetre by centimetre, the lock gate chamber will be sunk into the ground. This is done by dredging away the sand underneath the structure, using remote-controlled robot arms. Dredging is done fully automatically and monitored 24 hours a day and 7 days a week by CCTV cameras, sensors and measuring instruments installed under the floor of the lock gate chamber.

Connecting the dividing wall to the outer lock head

In the coming period, work will be carried out to connect the dividing wall to the outer lock head. This connection forms part of the future approach channel to the new sea lock. Work scheduled for the coming months are concreting operations for the anchor beams.

Northern and southern lock chamber walls

In the coming months, finishing work will be carried out to the northern and southern lock chamber walls, such as the installation of reinforcement steel, cover slabs, concrete formwork, concreting operations and the construction of anchors. The two lock chamber walls together will soon form the chamber of the new sea lock.

Completion of the lock gates

In a specially dredged out part of the future new lock chamber lies the lock gate for the outer head which is being completed on-site. In the coming months, electrical and hydraulic installations will be installed in this lock gate.

 

Related news

  1. News item
    11-06-2019

    The Lock Operation Centre (SOC) is almost finished. The outer facade of the main building has been completed. An emergency... read more »

  2. News item
    11-06-2019

    The name says it all: the letterbox cofferdam is narrow and deep. OpenIJ hired a special crane to excavate it. The cofferdam... read more »

  3. News item
    11-06-2019

    On an average working day, some 500 people are working on the construction site of the large sea lock in IJmuiden. This... read more »

  4. News item
    11-06-2019

    The lock gates arrived at the port of Amsterdam at the beginning of this year and the completion work is now in full swing.... read more »