The new sea lock - what's happening in January and February?

News item
07-01-2019
update nieuwe zeesluis 2019

The construction activities on the site of the new sea lock in IJmuiden are in full swing.  More than 200,000 m3 of concrete have now been poured and still more will be poured in January and February, including concrete for the inner lock head (number 1 in the picture) and for the lock chamber (number 3 in the picture). Also in January and February, work will continue on the completion of the lock gates and on the local control buildings - which are now taking shape (numbers 4 in the picture). 

The lock gates have arrived in the Netherlands

After a 44-day voyage from South Korea via Cape of Good Hope, the lock gates for the new sea lock finally arrived in the Netherlands on 6 December.  The lock gates - floating in the water - will be transported by tug from Rotterdam via IJmuiden to the OpenIJ Logistics Centre in the port of Amsterdam as soon as the weather permits. One lock gate will be moored in the lock chamber of the new sea lock to be completed on-site. The other two will be completed in the port of Amsterdam.

Inner lock head

At the inner head (number 1 in the picture), OpenIJ is busy with the final concreting works before the sinking operation of this lock gate chamber. Partitions are being installed in the lock gate chamber of the inner head to ensure that the caisson will remain stable during the sinking operation.

Cofferdam for the lock sill

As soon as the lock gate has been moored in the lock chamber of the new lock, the cofferdam for the lock sill (number 2 in the picture) will be closed. This will create the necessary space for the construction of the lock sill opposite the inner head.

Lock chamber

In the coming period, the final concreting of the southern and northern lock chamber walls (numbers 3 in the picture) will be carried out. The top of the concrete walls will be covered by what are called cover slabs. Cover slabs are steel plates installed as a smooth rounded finish on top of the brickwork covering the lock chamber walls.

Local control buildings

Also in the coming period, work will start on the construction of the local control buildings (numbers 4 in the picture) situated on both sides of the Lock Operation Centre. One will be built near the inner lock head; the other near the outer lock head. The lock gates can be operated and controlled from these buildings. Together, the Lock Operation Centre (SOC) and the local control buildings are responsible for the control and operating of the new sea lock.

Cofferdam for the lock sill

The cofferdam for the lock sill of the outer head (number 5 in the picture) has been sunk to its required depth. The future outer gate will run on the lock sill when the lock must be opened or closed. The lock sill cofferdam has been sunk to a depth of 22 metres below NAP.

Related articles

  1. News item
    12-11-2018

    Rijkswaterstaat, OpenIJ building consortium and Port of Amsterdam would like to know your opinion about the way we keep you... read more »

  2. News item
    12-11-2018

    Two weeks ago, the gates for the new sea lock at IJmuiden were loaded on a ship for transport from South Korea to the... read more »

  3. News item
    12-11-2018

    The new sea lock will be the largest sea lock in the world. This means that when the new lock will be used, more salt water... read more »

  4. News item
    12-11-2018

    Inspectors call the IJmond Sea Entrance Project an example project in the field of safety. All employees are involved in the... read more »