Delay in completion of sea lock

News item
03-07-2018
Artist Impression nieuwe zeesluis IJmuiden - Bron:ZUS

The new sea lock, which will be the world’s largest, will be opened later than initially planned. Dutch Minister of Infrastructure and Water Management, Cora van Nieuwenhuizen, informed the Dutch House of Representatives of the modified schedule for the completion of the lock near IJmuiden today. The sea lock will be completed 27 months later. The date will consequently be moved to no later than the end of January 2022.

The delay will not have any consequences for shipping traffic to and from the ports of the North Sea Canal because the existing Noordersluis lock will now remain operational longer. This does, however, mean that larger ships than is currently the case will not be able to call at our port.

The related press release (in Dutch) is available on the Directorate-General for Public Works and Water Management (Rijkswaterstaat/RWS) website.

The letter (in Dutch) from the Dutch Minister of Infrastructure and Water Management to the Dutch House of Representatives is available on the Dutch House of Representatives website. 

Port of Amsterdam’s response to delay in completion of sea lock

Port of Amsterdam has been informed that the new sea lock will become operational 27 months later than initially planned. The completion will consequently be moved to no later than the end of January 2022. This does unfortunately mean that larger ships than is currently the case will not be able to call at our port.

We regret this outcome of events. Since the Noordersluis lock will now remain operational longer, the accessibility of ports in the North Sea Canal Area will, in any event, not be compromised.

The Directorate-General for Public Works and Water Management (Rijkswaterstaat/RWS) has assured us that the ports of IJmuiden, Beverwijk, Zaanstad and Amsterdam will remain easily accessible in the next few years. It is therefore vital that the Noordersluis lock remains in optimum condition.

We remain of the view that the construction of the new sea lock – even with this delay – is an impressive infrastructure project which contributes significantly to the economy of the North Sea Canal Area. Port of Amsterdam has confidence in the successful continuation of the project.
 

Related news

  1. News item
    11-03-2019

    The new sea lock has to withstand enormous forces. To achieve this, hundreds of thousands of steel concrete reinforcement... read more »

  2. News item
    11-03-2019

    Innovations have been introduced in SHIP over the past few months. Shipping company Jumelet has been granted a permit to use... read more »

  3. News item
    06-03-2019

    In March and April, work will be carried out to the exterior facade of the Lock Operation Centre (SOC) (number 1 in the... read more »

  4. News item
    20-01-2019

    The first of a total of three lock gates for the new sea lock has arrived at IJmuiden today. The lock gate was towed by a... read more »